First, the basement of the external walls of water leakage project engineering basement waterproofing standard GB50108-2001 "underground engineering waterproof technical specifications" secondary waterproof rating. Basement exterior wall waterproof structure with self-waterproof concrete plus coil waterproof, 50 thick polystyrene board protective layer.
2.2 site preparation 2.2.1 external wall of the pull bolts should be cut off in advance, wooden blocks removed after the use of cement mortar smooth. 2.2.2 grass-roots should be clean, concrete joints processing flat, made at the corner of the yin and yang ...
Second, the basement of the external walls of water leakage construction preparation 2.1 Technical preparation 2.1.1 Selection of construction methods Waterproof engineering is related to the use of the project an important indicator, it is the construction process of a key project, difficult engineering. The choice of construction methods and programs has a direct impact on the quality of construction. The underground wall of the project SBS waterproofing membrane with hot melt method full construction. 2.1.2 before the start of the project, the first organization of engineering and technical personnel to enter the construction site, to understand the situation, to further understand the characteristics of the project to solve the contradiction between the construction technology and the implementation process. 2.1.3 technology before the end of the construction of waterproofing works by the professional foreman in accordance with the construction drawings and the existing national norms require the actual situation of the project to the construction team in writing to the end. The contents include construction site, construction sequence, construction technology, construction level, node fortification method, enhancement site and practice, project quality standard, guarantee the quality of technical measures. And after the field technical person in charge of the strict implementation of the audit.