Continuous beam cantilever hanging perfusion, the most reasonable construction period is how long

I would like to ask a joint (32m+48m+32m) continuous beam cantilever hanging basket perfusion, each phase of the most reasonable construction cycle is how long (in days), thank you

Answer:

How many blocks are designed, and the span is cast with a cantilever? Symmetrical pouring, an average of 4 days a piece of it, the two sets of hanging baskets, Block 0 to see your ability to design their own bar
And the weather is ideal. The highway is low, the theory is OK, the 12 days on the railway is the least time
Continuous beam of a block of the construction period of about 10 days to about 12 days, the 10 day is a bit illegal operation