Blow more than two times epoxy quartz mortar. Quartz sand and putty parts are used for leveling the base surface of the floor and increasing the coating thickness in order to improve the abrasion resistance of the floor. Because quartz sand filling rough, so floor paint mortar layer is relatively rough, there are more pores, the first mortar can effectively leveling floor paint construction surface.
Undercoat. It is necessary to use epoxy primer, the use of epoxy primer to the ground closed, so that the ground moisture and air can not reach the ground, in the bottom coating should also pay attention to the smoothness of the ground.
Stir。 The raw materials must be through mixing this step can be used in the construction process will use epoxy primer, epoxy paint, putty powder, epoxy mortar and their corresponding curing agent, these products are needed for mixing to use. For example, the mixing ratio between epoxy primers, finishes and between paint and curing agent is 4:1, especially in the summer, more attention should be paid to their mixing ratio. In summer, a small amount of curing agent should be added, and the mixture ratio is roughly 5:1. In quartz mortar, the mixing of quartz sand and water, mixing and mixing between putty powder and water, all of them should be mix and stir in the corresponding process.
Polish and clean the floor. Use the grinding machine to smooth the uneven ground. If there is a dent, fill it up with cement or putty. In sanding, make the whole surface smooth and dust-free, which is a basic part of the floor paint.