U type steel sheet pile generally has two kinds: one is the PU steel sheet pile, whose width is 600mm; the elastic bending moment from 600 ~ 3200cm3/m; reuse rate reached 30; very thick, suitable for high salinity, strong durability; two AU steel sheet pile, whose width is 750mm, the elastic cross section the surface resistance moment from 1410 to 2580cm3/m; and PU steel sheet pile compared to AU steel sheet pile is thinner and lighter but stronger; another angle, easy to pull out from the soil pile.
Steel sheet pile U type and Z type and AS type, the Z type and AS type steel sheet pile production, processing and installation is more complex, and the price is U higher than about 1/3, mainly used in Europe and the United States, Japan and South Korea and other Asian countries, mainly the use of U type steel sheet pile.
12m Larson steel sheet pile 450 machine, about 80 a day, according to the geological conditions and construction conditions and other factors, there are differences.

Share to: