1, according to the general layout plan on the mechanical layout requirements to determine. The tower crane's arm length should be swept to the required area, otherwise the worker's formwork and materials can not be transported vertically. (tower crane is the main tool to solve vertical transportation, and auxiliary tools are derricks and double cage elevators)2. After a project has been obtained, it is important to design the layout plan of the field machinery at first. It determines the position of the tower crane and uses several tower cranes, etc. it also conforms to the requirements of economic rationality.3, we should take into account the location of the tower crane, but also take into account the length of the tower crane, but also to meet the requirements of the site construction schedule.
How to choose tower crane in engineering:1, according to the general layout plan on the mechanical layout requirements to determine. The tower crane's arm length should be swept to the required area, otherwise the worker's formwork and materials can not be transported vertically. (tower crane is the main tool to solve vertical transportation, and auxiliary tools are derricks and double cage elevators)2. After a project has been obtained, it is important to design the layout plan of the field machinery at first. It determines the position of the tower crane and uses several tower cranes, etc. it also conforms to the requirements of economic rationality.3, we should take into account the location of the tower crane, but also take into account the length of the tower crane, but also to meet the requirements of the site construction schedule.
First of all, your engineering structure is reinforced concrete Or steel? What's the weight of the lift? The lifting capacity of tower cranes should meet the needs. Generally speaking, steel structure hoisting, tower crane of the largest lifting weight and gravity moment should be large; hanging steel reinforcement of a smaller can.Secondly, the boom length should be covering the scope of construction (can also be arranged to meet several sets of crane lifting coverage). But in the 360 level luffing jib range, can not have obstacles (other cranes and buildings), and the boom and the distance between them (below) should be not less than 2m.Third, in the construction project is relatively high, the site is relatively small, you can mount the internal climbing tower crane. Building covers a large area, sometimes one can solve the problem. Of course, it is more troublesome to disassemble and lift inside, but the standard section used is less and the cost can be lower.