1, start pouring room, finished room 2, mix proportion condition on the site: Cement: Sand: Stone: Water: 3, Metering conditions on the site: cement lack of KG sand lack of KG stone lack of KG water lack of KG (plus vehicle weight case) concrete step exemption 4, concrete slump casual inspection does not comply with the requirements of mix proportion 5, record the number of sets of concrete specimen and intensity of the construction unit; 6, record pouring thickness of cusion layer, elevation condition and pouring sequence (which axis)