Home > categories > Construction & Real Estate > Cement Boards > How to put tiles on the cement board
Question:

How to put tiles on the cement board

How to put tiles on the cement board

Answer:

1, tiles to use cement, those bags to the construction team to do, to pay special attention, they are not responsible for maintenance, often shoddy, with poor quality cement, each bag can be less 5 yuan, they can earn more than 200 yuan The 2, in the smooth cement wall, the ground is calendering. In the shop before the wall and the ground should be hair. Can not put the brick directly on the wall paint above. 3, in the original tile on the floor of the new floor tiles, the original floor tiles must first knock down and then shop! Otherwise it is difficult to affix. 4, floor tiles often used dry shop, wall with wet shop. 5, with light steel keel, cement board bag riser, in the cement board on the tile, to hang wire mesh. Or easy to fall out.
Often these are done on man-made walls or after the pillars have to be done. because. When you need to paste that wall, the cement mill should be dry.
In the partition on the tile is generally the most common is: first need to paste the tiles with a grid (0.5X0.5) with 30 straight row nail fixed, so after a thin layer of cement on its bottom (select Thinner because when you have finished the wall after the finished tile thickness of about 4CM, if your bottom is too thick; in the passage of time there will be cracks, which is the overall wall in the wall caused by the top of the pull. So it is thin) and so on when it can quickly paste through the dry.

Share to: