On the problem of the hanging basket preloading procedure? Construction of the two main piers, the progress of the first, the previous one to hang the basket pre pressure, then the second need to pre pressure?

Answer:

Install side span closure section, installation of hanging mold closure segment skeleton, formwork, steel banding, installation of prestressed pipe and the core concrete pouring, side span closure segment and maintenance - tension closure segment longitudinal, transverse and vertical prestressed grouting, removing the side line and cross - - side span closure segment construction support the landing gear box girder.
The previous one carried out the pre pressure of the hanging basket, then the second still need to pre pressure. Should be with an operation
On the problem of the hanging basket preloading procedure? Construction of the two main piers, the progress is divided into