Question:

Tunnel construction sequence What is the sequence of construction process

The tunnel has the super big pipe shed and the lead small conduit, is carries on the blasting excavation first or carries on the advance support first, has the anchor rod in the tunnel, this between the construction craft order is any

Answer:

Closed arch fill concrete pouring pouring arch fill fill arch wall waterproof plate arch wall steel reinforced concrete side wall chisel template trolley in the end of the work of the arch wall two lining concrete
The excavation of invert waterproof plate, blind pipe and steel bar at the bottom of the tunnel, and the pouring of invert arch
Measuring and setting out the drill hole charge blasting, ventilation, smoke exhaust, water spraying and dust removing, the top of the vertical arch, the anchor rod and the reinforcing steel net, the spraying concrete operation enters the next cycle, and the first branch is stabilized and then the two lining is applied