10 meters span, from 1 meters high slope, need to use the big beam? What size of steel is welded?
How long m, single slope or double slope, a few m bays, columns high m, etc., data integrity
Ten meters span is single or double slope slope, single slope, the slope is 10%, double slope, the slope is 20%, but such small span steel, direct line, speed, although the steel key, but processing simple labor costs.
The span of 10 meters, 1 meters high slope, if the bay is 6 meters, can be welded I-beam, H220 x 180 x 6 x 8, side span to horizontal support, if the length of 30--60 meters, is set in the middle of a level of support, if the length of 60--90 meters, is set in the middle of the two horizontal support beam with the beams in the middle are advised to set up a horizontal tie.