In the construction of the bridge, the construction of the beam (usually continuous beam) is from the pier symmetrically to both sides. The utility model relates to a device which is arranged at the end part of the support and is used for fixing the beam template.
In summary, the construction process of the hanging basket construction management, said the following simple way: the hanging basket can be moved forward in place to install the bottom mold and the mold to install the bottom plate and the side rib reinforced pipe, and reserved installed within the mold to install roof reinforcement and pipe, concrete pouring and curing the reserved to wear pre stress steel beam and tension anchor a pipe grouting.
The tension must be carried out after 90% of the design strength, and in accordance with the order of the transverse beam of the top plate of the web. At the end of the tension, the grouting is carried out immediately, and after the grouting is finished, the hanging basket can be moved forward, and the construction of the next section of the box girder can be carried out.