Each layer requires ramming machine in the construction standard of soil thickness after compaction or virtual shop
The paving thickness of each layer is paved
According to the "backfill engineering construction technology standards" provisions of GY1103-2003 3.2.5 on each layer thickness, each layer compaction regulations, breaststroke ramming machine thickness of soil layers is 200~250mm, each layer of compacted 3~4 variables.
Each layer requires ramming machine in the construction standard of soil thickness is the virtual shop
According to the "backfill engineering construction technology standards" provisions of GY1103-2003 3.2.5 on each layer thickness, each layer compaction regulations, breaststroke ramming machine thickness of soil layers is 200~250mm, each layer of compacted 3~4 variables.