Electric power equipment start-up and commissioning of the project there is a difference?
The difference is that one is the equipment debugging, testing period to start, one is in the formal production of the time to start.
After a single commissioning, and then linkage test, after the test, such as no-load, put into operation in the above steps are completed, the test is no problem, start running with load.
The start of the equipment is started in the single test.