Find the demolishing scheme of scaffold
Removal of scaffolding shall comply with the following requirements:11.2.1 removal operations must be carried out from top to bottom, prohibited from top to bottom operation at the same time;11.2.2 even wall pieces must be removed with the scaffolding layer by layer, is strictly prohibited even after the first wall or a few layers of the demolition of the dismantling of scaffolding; demolition of the height difference should not be greater than 2 steps, such as the height difference is greater than the 2 step, should be added to strengthen the wall;
11.2.3 when the scaffold is removed to the lower part of the last long pole height (about 6.5m), should be in the appropriate position to set up temporary support reinforcement, and then dismantle the wall;11.2.4 when the scaffold is divided into sections and sub sections, the two ends of the scaffold without dismantling shall be provided with the connection of the wall and the lateral bracing.
Removal methodThe development of the demolition plan, the program should include the removal of the steps and methods, safety measures, etc.. Demolition order should be observed from top to bottom, the first after the demolition, after taking the first demolition principle. That is, first remove the railings, scaffolding, scissors support, diagonal bracing, and then small beams, large cross bars, vertical poles, etc., and according to the principle of one step clear in order to be prohibited from top to bottom at the same time the demolition work. Remove the shelf of the high-altitude personnel should wear safety helmet, safety belt, wear soft shoes on the shelf, at the same time, around the railing or set up a warning sign and a special command, in order to avoid casualties.