Fixed in the construction of steel tubular scaffolding 3 rows of what is meant
The scaffold is common in interior formwork support, generally in the plane projection matrix, identified in the upper load situation, through the relevant calculations to determine the vertical and horizontal spacing, vertical rod erection step rails to ensure the bearing capacity of the frame body.
Double row scaffolding as the name implies, is composed of two rows of independent vertical rod through a small bar, a large bar member connected to the temporary bearing frame body, a common fastener tubular steel scaffolding, scaffolding, construction building frame periphery is currently the most common form of.
Generally divided into single row scaffolding, double scaffolding and full scaffold.Single row scaffolding, the frame body is composed of a vertical rod; because of its small application scope (generally used in the decoration construction), poor stability, building height is small, has gradually withdraw from the market.