Detailed construction technology
This is a fixed mode it, learn more like Oh
This you have to do more dynamic technology can ah, or certainly not work!
Process flow
The ceiling of the standard high-level cable → designated keel sub-line → installation of water and electricity pipeline facilities → installation of the keel → installation of small keel → anti-corrosion treatment → installation panel → installation of pressure
1) Pace line: According to the level of the floor level, along the wall high to the ceiling design elevation, along the walls around the ceiling elevation level, and in the four weeks of the elevation line of the keel of the sub-file position line.
2) Install the large keel: the embedded steel will be bent into a circular round hook, wear 8 # galvanized iron wire or Φ6-Φ8 bolts will be fixed, and ensure that the design elevation. Ceiling arch according to the design requirements, design requirements for the room when the general span of 1 / 200-1 / 300.