Crack: tiles shop after 24 hours to clean up the hook, hook before the first floor of the gap should be wiped with impurities, with a special sealant joints. Clean up: in the home decoration tiles construction process with the dry with the clear, after the completion of (generally should be after 24h) and then cotton yarn and other objects on the surface of the brick. The quality of floor tiles: floor tile clean, clear pattern, consistent color, uniform seams, the surrounding straight, hook seam smooth, plate without cracks, angle and lack of shock phenomenon.
Pre-shop: First of all, should be based on the design requirements of the drawings, the tiles of color, texture, surface formation and other rigorous selection, and then in accordance with the requirements of the pre-shop drawings. For the pre-shop may appear in the size, color, texture error, etc. to adjust, exchange, until the best results, according to paving smoothly stacked neatly spare. Paving: laying the selection of 1: 3 dry hard cement mortar, mortar thickness of about 25mm. Paving before the tiles on the back of the wet, to be a dry front is appropriate Put the tiles in accordance with the requirements on the cement mortar, with a rubber hammer tapping the floor finishes until the dense formation to meet the requirements.
Base treatment: the dust, debris thoroughly cleaned, no hollowing, cracking and sand and other defects. Pin line: before the construction of the wall around the height of the pop-up control line, in the ground pop-up cross-line to control the floor tile size.