How to carry out paving operation of self-propelled asphalt mixture paver?
The paving process of self-propelled spreader is as follows:1. according to the construction requirements, set the width of the paving, paving thickness, paving speed and vibration vibration and other related parameters.2. after the start of paving, paving the top lorry at the grassroots level, while traveling on the road side of the mixed material on the receiving hopper.3. the mixture in the receiving hopper is transported to the rear of the mainframe by the scraper conveyor.4. the mixture which is sent to the back of the mainframe is conveyed to both sides of the whole ironing device by the screw conveyor.5. the ironing device moves forward under the traction of the main engine. The mixture is compacted and compacted to form a flat and dense paving layer for further compacting and forming of the roller.6. automatic or manual control during paving operation to ensure the width, thickness, cross slope and degree of compaction of the paving
The first step is to install the ironing board as requiredThe second step is to draw a good technician guide line of Paver Screed underlying good pre paving hardness Garzon paving coefficient thick board or woodThe third step to reversing car pull incoming paver hopper lifting hopper, paving machine manual with the helical mixture and then spiral vibration and to automatically find the instrument set to automatic position, push the lever forward, paving speed according to the requirements set.
The spreading process of self-propelled paver is as follows: 1. according to the construction requirements, the paving width, paving thickness, paving speed and vibration vibration parameters are set. 2. after the start of paving, paving the top lorry at the grassroots level, while traveling on the road side of the mixed material on the receiving hopper. 3. the mixture in the receiving hopper is transported to the rear of the mainframe by the scraper conveyor. 4. the mixture which is sent to the back of the mainframe is conveyed to both sides of the whole ironing device by the screw conveyor. 5. the ironing device moves forward under the traction of the main engine. The mixture is compacted and compacted to form a flat and dense paving layer for further compacting and forming of the roller. 6. automatic or manual control during paving operation to ensure the width, thickness, cross slope and degree of compaction of the paving. Asphalt paver working process of new telescopic asphalt paver with the rapid development of China's highway construction, road construction machinery for the increasing demand, the asphalt paver road machinery as one of the most important, in highway construction has played an irreplaceable role. The new telescopic asphalt paver is widely used in the field of road construction due to its flexible ironing plate and suitable for the construction of different width of pavement.