Question:

How to put the concrete on the tunnel

What are the steps? If you build a template, how to fill in the concrete. The tunnel is to dig all the generalist pouring, or digging into the side. Simply say. Better picture. In addition, we have seen a video, the shield machine to dig up the tunnel after the installation of a number of prefabricated panels, but these prefabricated plate is curved. Do not have to fill in a semicircle tunnel?

Answer:

Pouring should be set up before the template, the concrete template will be about 50mm*50mm of the pouring bin.After the excavation of the shield, the top arch and the top arch of the casting template are separated, so you can see the situation similar to the arc.
Two lining trolley consists of two parts, one is the erection and welding of steel trolley, and the other is pouring trolley.
Tunnel concrete is completed by the way of edge excavation and lining. After the excavation, the shotcrete is used as the initial support, and then the reinforcing steel mesh is set up. Only after the two lining.