In the construction process of reinforced concrete frame structure

In the process of construction of reinforced concrete frame structure, the main contents of the quality inspection and monitoring of formwork engineering

Answer:

The axis of elevation, position, size, the whole corridor high verticality deviation, lateral bending deviation, arch camber, surface roughness, plate seam, embedded parts and reserved hole is correct
The specifications, quality and fastening conditions of all kinds of connecting pieces and supporting parts (the use of torque wrench for fasteners); 3, the overall stability of the supporting points and the combined steel formwork;
Template construction inspection items: 1, the template and the layout and construction of the scaffold is in line with the special construction organization design (program) and safety measures;