In the construction of the formwork support frame must be equipped with vertical and horizontal floor bar? Built in 26 meters of concrete surface, set up a height of 3.6 meters

Answer:

According to the JGJ130-2011 (construction of steel tubular scaffold safety technical specifications), article 6.3.2 provides that the scaffolding must be equipped with vertical and horizontal sweeping rod. Vertical sweep rod should be fixed at right angles from the bottom of the steel pipe is not more than 200mm of the vertical pole. The transverse sweeping rod shall be fixed by a right angle fastener close to the vertical rod below the vertical sweeping rod.
For the formwork support, the floor must be set to sweep the floor, no matter how high the height of the frame
The bottom of the frame of the sweeping rod must be set in place, and must be vertical and horizontal layout.