Foundation treatment to find leveling to pay attention Five to: 1 slope accurate, smooth drainage 2 surface is flat 3 strong 4 clean 5 dry
Coil ply attention Paving direction, slope less than 3%, parallel and roof paving, slope greater than 15% or roof vibration, perpendicular to the roof paving. Slope between 3% to 15%, can be parallel to the vertical; membrane waterproof roof slope should not be greater than 25%. The upper and lower layers may not be piled on each other.
Three do 1 to do concrete or mortar ratio is accurate 2 to do the surface of the second calendering 3 to be fully maintained
Four do not: 1 surface can not afford sand 2 surface can not afford skin 3 surface is not crisp 4 does not crack