Position of horizontal construction joint of shear wall. The first layer is higher than the standard layer, the large template in accordance with the standard layer, the first part of the difference with the roof can be poured?
The project is from the construction point of view. From the point of view of construction joints should be left in the column 1/2 high as well, where the shear is small. Consistent with the principle of beam slab stay within the 1/4.
Large template in accordance with the standard layer, the difference between the first part of the roof can be poured?
Position of horizontal construction joint of shear wall. The first layer is higher than the standard layer height