Inspection process, for there is a significant risk of hoisting machinery, such as special operating environment, frequent accidents, etc.), the inspection institution approved by the provincial quality technical supervision department agree, can shorten the cycle of periodic inspection appropriately, but the shortest period of no less than 6 months.
Small light lifting equipment, bridge crane, gantry crane, portal crane, cable crane, mast cranes, rail crane, jib crane, once every 2 years mechanical parking equipment, including the lifting of molten metal and hot metal crane 1 time every year. Performance test of the rated load test, static load test, the dynamic load test project, the first test and the first periodic inspection must be carried out, the rated load test program, after 1 inspection cycle 1 time intervals
Article 5 the provisions of article 5 of the regular inspection rules for hoisting machinery issued by aqsiq: The periodic inspection period of the crane machine is as follows: (1) tower cranes, elevators and floating cranes are once a year; The wheel of the wheeled container crane is made up to 1 times every two years.

Share to: