Home > categories > Machinery & Equipment > Pile Driver > What are the requirements for lime mud piling machine?
Question:

What are the requirements for lime mud piling machine?

What are the requirements for lime mud piling machine?

Answer:

On the whole, the more sticky the better, but some places are not so good, economically speaking, just take it. I'm a driver of the piling machine. Contact me if you need me
Cohesive soil content is not greater than eight percent, the more sticky the better
It can increase the specific gravity of mud and play the role of wall protection
Even with loess, we should pay attention to its sediment concentration rate can not be too large, the greater the viscosity, the liquid limit to be high, plasticity is better, it is best to add thousands of cents when the Loess pulp, industrial soda ash (that is, sodium carbonate).
Are you talking about bored piles? The slurry is strictly not added with yellow mud, and the best result should be made from bentonite slurry.

Share to: