In the process of high-rise building construction, bowl buckle type steel pipe scaffolding foundation and foundation treatment should meet the requirements
Landing bowl-scaffold when erecting height H is less than or equal to 20m according to the ordinary routine shelf erection, erection of a height when H > 20m and ultra high, heavy and large span of the template support system must make special construction design and structural analysis and calculation.
In fact, the construction of high-rise building scaffolding over a certain height, should be carried out economic comparison, otherwise, the height of a one-time erection is too high, the cost will be high.
The foundation and foundation treatment of bowl buckle scaffold should meet the requirements of standard JGJ166.