Question:

What is the role of the grid steel frame and steel mesh in the power tunnel

What is the role of the grid steel frame and steel mesh in the power tunnel

Answer:

Advanced small pipe grouting small catheter with a diameter of 32-50mm steel pipe, the pipe tip and tube holes for special processing. The first row with drill drilling pipe. Row spacing is 30cm, fan shape, elevation of 5 degrees to about 8 degrees. The length is 2.25m, a single fluid grouting (cement) or double grout (cement water glass slurry). Adjust the grouting pressure according to the soil.
The back cover, shaft ingate construction, to get rid of the upper advanced small pipe grouting reinforced concrete, erecting of ingate upper grille steel frame, injection, get rid of the upper concrete lower reinforced concrete, erecting of ingate to spray the concrete lower grille steel frame.
The production of the grid steel frame component production and installation grid steel frame component is suitable for the production of the steel frame of the initial lining and the support of the digging tunnel. The steel grid with steel and steel by welding is composed of steel frame, steel grille by assembling (bolting, welding) after the formation of the steel arch structure after initial support structure of sprayed concrete, which is applied in soft soil tunnel structure is the most effective measure.
Function as follows:1, the construction of the shaft excavation of the power tunnel shaft structure is a permanent structure, the construction of the shaft using shotcrete + net structure steel frame + steel mesh support + waterproof film + cast-in-place reinforced concrete lining method.