Question:

When the hanging basket method is used for the construction of continuous beams, the adjacent fast

Hanging basket construction continuous beam, the adjacent fast is how to connect, such as Block 0 and block No. 1

Answer:

4, pouring the whole section of the next section, until the strength of more than 80% after the design, before and after the left and right sides of the steel cable.5, in the long hole bellows (such as 1# to 0# to 1 "# long hole grouting filling) within reach the design strength, namely two adjacent segments after connection.6, 2# segment connection (2 ', 1 #' #, 0# block, 1#, 2# in steel wire connection).7, 3# segment connection (3 ', 2', 1 # # '#, 0# block, 1#, 2#, 3# in steel wire connection). The remaining segments are, in turn, connected like strings of pearls.
3, installation of connecting two adjacent segments (such as 0# and 1#, 0# and 1 "#) corrugated pipe hole, and wear long (such as 1# to 0# to 1" # through wearing steel strand).
1, have been pouring section (such as 0# block) of the end of the concrete to do all the processing of cutting hair.2, the first of two adjacent segments (such as 0# and 1#, 0# and 1 '#) all the longitudinal bars between the (steel web comprises a bottom plate, the roof and corresponding welding together).