Hanging basket construction continuous beam, the adjacent fast is how to connect, such as Block 0 and block No. 1
4, pouring the whole section of the next section, until the strength of more than 80% after the design, before and after the left and right sides of the steel cable.5, in the long hole bellows (such as 1# to 0# to 1 "# long hole grouting filling) within reach the design strength, namely two adjacent segments after connection.6, 2# segment connection (2 ', 1 #' #, 0# block, 1#, 2# in steel wire connection).7, 3# segment connection (3 ', 2', 1 # # '#, 0# block, 1#, 2#, 3# in steel wire connection). The remaining segments are, in turn, connected like strings of pearls.
3, installation of connecting two adjacent segments (such as 0# and 1#, 0# and 1 "#) corrugated pipe hole, and wear long (such as 1# to 0# to 1" # through wearing steel strand).
1, have been pouring section (such as 0# block) of the end of the concrete to do all the processing of cutting hair.2, the first of two adjacent segments (such as 0# and 1#, 0# and 1 '#) all the longitudinal bars between the (steel web comprises a bottom plate, the roof and corresponding welding together).