Glass wool external wall insulation construction shceme: in this project, 50 thick glass wool thermal insulation boards are used, which has became popular in Beijing as external wall thermal insulation material only in recent two years so there are no mature check, acceptance and construction specifications. It is constructed according to the design negotiations, the reference standard, Atlas 10BJ2-11, JGJ144-2004, GB50411-2007. Construction of glass wool is difficult. Therefore, construction scheme should be made according to specification and design requirments and negotiation records before construction. At the same time, we should strengthen control during construction and solve problem immediately and construct in strict accordance with Atlas and technical schedule. The insulation construction period of this project is 20 days. It is very tight so we need to make proper arrangement to ensure insulation construction period. Dingfuzhuang Middle School insulation construction: first teachingl buildings, then laboratory buildings, finally canteen. When the outer scaffolds are all constructed in the teaching building, carry out construction in four facades of the teaching building from bottom to up. When the laboratory building outer is sprayed with concrete, carry out laboratory building outer thermal insulation construction. At this time, more workers are needed to ensure insulation constructions of two buildings carried out simultaneously as the teaching building insulation constructio is not finished. When the insulation project is constructed in canteen outer, add more workers to ensure insulation constructions of the three buildings carried out simultaneously.
Glass wool external wall thermal insulation construction scheme 2 main material preparation: A, glass wool insulation board (80mm thick) (30mm thick) B, anchorage (8X120) mm plastic rose nail C, sample plate. This place belongs to south podium buildings, where large-scale construction can only be carried out after checking and confirming of supervision main contractor from Party A . 3.6 Pre-construction preparation 3.6.1 Set control lines in necessary parts of the building external wall internal and external corners, holes and deformation joints and rustication. Snap the horizontal ink line on the holes of door and window, and the glass?wool?board in first procedure while controling levelness in construction. Set the horizontal control line in places with two vertical control lines to control the flatness in construction of glass?wool?board. 3.6.2 Except for the solid wall, the wall surfaces should be coated with cement mortar and the flatness, intensity and verticality of mortar surface should meet the requirements of relevant specification. Base plane should be smooth, firm, dry, clean, water and alkali resistance, chalking resistance, PH value

Share to: