Bathroom decoration is to first paste tiles and flooring or to install the first water heater and toilet? Have to say that the next thanked
Wall plastering - ground waterproof - wall stickers - install the toilet - floor stickers water heater generally use expansion bolts, without damaging the wall tiles (refers to the wall is not broken pieces of the case), are generally wall Brick stick finished after installation!
The first to install the installation of water heaters and toilets need to pay attention to the investigation of the tap water, drainage pipes, and then began to paste tiles, floor, and finally install the water heater and toilet and other sanitary equipment.
First wall waterproof 2-3 times after the wall, from the height of 300 mm above the paste, and then do the ground waterproof, 2-3 times, and then paste the tiles and 300 mm around the place and then installed water heater, ceiling,