Question:

Case Study of Aluminum Alloy Formwork

Case Study of Aluminum Alloy Formwork

Answer:

For example: the beam section of the project is larger, the design of the beam at the end of the support with double column support, pole spacing 1200mm, beam at the end of the plate, the beam at the end of support aluminum beam 125mm wide, arranged on both sides of the beam at the end. Aluminum sheet 4mm thick.
Aluminum alloy template lighter than the steel template, the use of fast assembly and disassembly system, moving components, lightweight and flexible, greatly reducing the amount of artificial, easy construction management. Aluminum alloy template is one of the most advanced templates, the construction company image is good. Design advanced early demolition system, to speed up the construction progress.
Engineering aluminum alloy template design program case: 1, all using stereotypes design, factory production, template engineering quality excellent. 2, safe and civilized construction, people-oriented, scientific development. 3, because the scene almost no production process, reduce the construction noise, energy saving, power in the future.

Share to: