Labor costs, materials costs, machinery costs accounted for the total cost of the project
Industrial buildings are mainly equipment valued for larger ones. Labor costs 13-16%, material costs (including equipment) 62-68%, mechanical costs 5-8%, and the rest is safety civilization, management fees, profits, fees, taxes
General civil construction: labor costs 18-21%, material costs 50-55%, machinery costs 8-11%, the rest is safety, civilization, management fees, profits, fees, taxes