Installation condition of 3.2 tower crane3.2.1 tower crane has special equipment manufacturing license, product certification, manufacturing supervision and inspection certificate, the tower crane manufactured abroad should have product certification, and has been in the construction administrative departments for registration.3.2.2 tower cranes shall be of complete structure and conform to the provisions of GB5144 "safety regulations for tower cranes".3.2.3 under the following circumstances, tower cranes are not allowed to use:If the state has been eliminated from the designated period of time, exceeding the prescribed service life assessment, the safety devices and safety facilities can not meet the safety and technical standards of the state or industry; there is no complete safety technical file.3.2.4 tower cranes must be maintained and fully checked before they are installed. Structural parts with visible cracks, severe corrosion, overall or partial deformation, connecting shafts (pins), Kong You, severe wear and tear should be repaired or replaced, in accordance with the provisions of the installation.3.2.5 tower crane foundation should meet the requirements of the use manual, the carrying capacity of the foundation must meet the requirements of tower crane design, installation should be carried out before the hidden project acceptance, qualified before installation. Slope and drainage facilities should be built around the foundation.The track foundation and track laying of 3.2.6 walking tower crane shall be carried out according to the instruction manual and shall comply with the provisions of GB5144.
Please refer to the technical regulations for the safety of installation, disassembly and use of tower cranes in construction;The following is copy:3 installation of tower cranes3.1 conditions for installation of tower cranes3.1.1 tower crane installation unit must have the construction administrative departments issued the contracted professional qualification and heavy equipment installation engineering construction enterprises safety production license. Tower crane installation units must be engaged in the installation of tower cranes within the scope of qualification permit.In addition to the professional and technical personnel who have the qualification standard, the installation units of 3.1.2 tower cranes shall also have professional personnel who are in line with the project. The person in charge of the project, the project manager and the full-time safety management personnel shall have the certificate of safety production inspection. Tower cranes, installers, electricians, drivers, signal engineers, cable operators should have special construction operation qualification certificates.3.1.3 construction units shall sign professional contract for installation engineering with the installation units, and make clear the responsibility of both sides for safety in production. In case of general contracting of construction, it shall be signed by the general contractor and the installation unit.