Home > categories > Construction & Real Estate > Stairs > Shanghai 2000 quota, staircase template and concrete how to calculate? What is the difference between the list and the list?
Question:

Shanghai 2000 quota, staircase template and concrete how to calculate? What is the difference between the list and the list?

Shanghai 2000 quota, staircase template and concrete how to calculate? What is the difference between the list and the list?

Answer:

The list of templates and concrete calculations are the same as above, but the difference is that the list template is included in the measure fee.
Do not deduct less than 500mm staircase wells occupied area. Staircase stepping, stepping board, platform beam and other side templates, no other calculation. Concrete is calculated in real terms. Quota is included in the project direct fee.
The staircase and the floor are divided by the outer edge of the staircase beam, which is included in the horizontal projection area of the staircase.