Question:

The relevant provisions of the demolition of the external wall scaffold:

Do the external wall decoration (from the top down to do) scaffolding is to wait until after the completion of the indoor and outdoor decoration before the demolition?If the first interior decoration, can make a layer of a layer of it is to remove all the work finished I mean I finished all the interior decoration, wall decoration only, then I do a wall decoration on the demolition of a layer of scaffolding, this site useful no

Answer:

Three, discharge should meet the following requirements:1, the structure is strictly prohibited to throw to the ground;2, transported to the ground should be timely inspection of the construction parts, repair and maintenance, and according to the varieties, specifications at any time yard storage.
Two, removal of scaffolding, should meet the following requirements:1, the demolition work must be from top to bottom layer by layer, prohibited from top to bottom operation at the same time;2, even the wall must be removed with the scaffolding layer by layer, is strictly prohibited even after the first wall or a few layers of the demolition of the demolition of the scaffolding; demolition of the height difference should not be greater than 2 steps, such as the height difference is greater than the step, should be added to strengthen the wall;3, when the scaffolding down to the bottom of a long rod height (about 6.5m), should be in the appropriate position to set up temporary support reinforcement, and then dismantle the wall;4, when the scaffolding to take the sub section, the demolition of the sub elevation, the demolition of the scaffold should not be removed at both ends, should be added to the wall and lateral oblique reinforcement.
The relevant provisions of the demolition of the external wall scaffold:First, the removal of scaffolding before the accurate preparation work should meet the following requirements:1, should be a comprehensive inspection of the scaffold fastener connection, even wall pieces, support system, etc. are in line with the requirements of the structure;2, should be based on the results of the inspection to improve the construction organization design of the demolition order and measures, approved by the competent authorities before the implementation;3, should remove the scaffolding on the debris and ground obstacles.