What is the treatment of concrete pump block
When the occurrence of blocking, should immediately take the method of repeated positive and reverse pump, and gradually make the pump out of the commodity concrete suction hopper re-mix and then transport.
After pumping the finished concrete, be sure to use high pressure water to pump and S tube rinse.
Into the hopper into the 15 ~ 30L cement slurry, repeated, forcing the channel to open.
So that the pump reverse run to destroy the agglomeration, so that the commodity concrete back to the hopper to re-stir, and then positive pumping.