Which is the main basis for the disassembly and assembly process planning of tower cranes?
Before the installation and disassembly of 2.0.10 tower cranes, special construction plans shall be worked out to guide operators to perform installation and disassembly operations. The special construction plan shall be prepared according to the actual conditions of the product specifications and the working site of the tower crane, and shall comply with the requirements of the relevant laws, regulations and standards. The special construction plan shall be examined and approved by the technical, safety and equipment departments of the unit, and approved by the technical person in charge, and shall be approved by the supervision unit.2
12 installation process;13 safety device debugging;14 major hazard installations and safety technical measures;15 emergency plan.2.0.12 tower crane disassembly special program should include the following content:1 project overview;2 plane and elevation of tower crane position;3 disassembly order;Weight and suspension position of 4 parts;5 disassembly type, performance and layout of auxiliary equipment;6 power settings;7 construction personnel allocation;8 rigging and special tools;9 major hazard installations and safety technical measures;10 emergency plan.
.0.11 tower cranes should be prepared before the installation of special construction program, and should include the following contents:1 project overview;2 installation location, plane and elevation;3 types of tower cranes and technical parameters of performance;4 basic and attachment device settings;5, climbing conditions and adhesion nodes detail;6 installation sequence and safety quality requirements;7 weight and suspension position of main mounting parts;8 installation of auxiliary equipment type, performance and layout;9 power settings;10 construction personnel allocation;11 rigging and special tools;