If it does not contain material, only manual and mechanical, how much is the price per square meter?
First of all, it depends on how large your mixing station is and how many tons of material can be produced per hour.. Normal 4000 of the station, one day plus class 13--14 hours, more than one kilometer to play, the most critical is the spreader machine speed can not slow, 8--9 meters
How thick do you want to shop? Whose machine is it? Domestic imports? Money and who is out? Do you pay by the day or by the bill? These are not clear, you are difficult to say this question
Ha-ha。。 If you ask this question, you will see that you are a layman.. You ask how many meters a day can be laid.. First of all, it depends on how large your mixing station is and how many tons of material can be produced per hour.. Normal 4000 of the station, one day plus class 13--14 hours, more than one kilometer to play, the most critical is the spreader machine speed can not slow, 8--9 meters