Home > categories > Construction & Real Estate > Curtain Walls > Building curtain wall embedded parts need to do what project testing
Question:

Building curtain wall embedded parts need to do what project testing

Bought a group of four foot embedded parts, one of which with the steel welded root fracture, so want to do the relevant test to see whether the use of these pieces of embedded products? Where is the test? Specific detection of those projects? How much does that cost?

Answer:

Generally do the yield strength of steel, tensile strength, elongation and cold bending and other tests. Sent to the local professional testing of qualified testing units testing, usually 60 tons a batch. The cost of a batch of 100 to 200 yuan, the local some differences.
On the building curtain wall embedded parts detection: 1, curtain wall embedded parts based on the detection of "concrete structure after the anchor technical regulations." 2. Detection of planting bars and bolts is 1/1000, as a group. There are three in a group. 3, glass curtain wall acceptance should provide information (1), curtain wall construction drawings, calculations, design instructions and other documents (2), the construction design unit to confirm the design of the curtain wall documents. (3), curtain wall used in a variety of materials, hardware accessories, components and the formation of product certification, performance testing reports, approach acceptance and re-inspection report. (4), curtain wall works used in the identification of silicone rubber certificate and proof of sampling. Import of silicone rubber inspection certificate. Experimental Report on Adhesion and Peel Adhesion of Silicone Fabrics by Specified Testing Organization. Report on the Pollution Resistance of Sealants for Stone. (5), post-embedded parts of the field drawing test report. (6), wind wall pressure test report, air permeability, rainwater permeability and plane deformation performance test report. (7), the temperature of the curing environment, the humidity records of two-component silicone adhesive mixing test records and pull off the experimental record. (8), lightning protection device test records. (9), hidden engineering acceptance records. (10), curtain wall components and components of the production record, curtain wall installation and construction records.

Share to: