Home > categories > Electrical Equipment & Supplies > Transformers > How long does it take to restart the transformer?
Question:

How long does it take to restart the transformer?

How long does it take to restart the transformer?

Answer:

What are the requirements for the commissioning and outage of the transformer? A: (1) the new operation of the transformer must be rated voltage under the impact test 5 times, overhaul after the impact test 3 times. (2) the transformer put into operation when the first cooler, cooler running for a period (about 15min) time, until the oil temperature is no longer rise and then stop. Disconnect the transformer first. (3) 110kV and above in the neutral point direct grounding system, put into operation and outage transformer, the operation must be grounded before the neutral point, after the operation and then decide whether to decide whether to disconnect. Transformer neutral point access to the arc suppression coil should be first after the exit. The neutral point of the two transformers should not be connected to a neutral bus with an arc suppression coil.
(4) power failure operation, the first load side of the switch, after the power side of the switch (multi-side power from low to high stop); first pull the transformer side of the knife, after pulling the bus side of the switch. Power supply operation is reversed. (5) into the backup transformer, the device should be based on the actual location and instructions to determine the load has been taken in order to make the operation of the transformer power failure. Diagonal and 3/2 wires on the transformer, although the transformer has been out of power, but the transformer's heavy gas and differential protection action can still cause its ring side of the switch trip. Should be based on the actual situation and the site of the gas protection to change the signal location or retreat gas out. (6) station transformer does not allow long-term side by side. Can be used to cut low-pressure low-pressure side of the cutting machine, with high-pressure knife cut off the station with a transformer.
If the transformer is shut down for a month or on hold, the trial is stopped for more than 6 months before the commissioning? A: The transformer shut down for a month, before the resumption of power transmission should be measured insulation resistance, qualified to be put into operation.Post or outage for more than 6 months of the transformer, should be done before the insulation resistance and insulation oil pressure test Dry and cold areas of irrigation and drainage dedicated transformer, the suspension period may be appropriate to extend, but not more than 8 months

Share to: