Home > categories > Machinery & Equipment > Tower Cranes > How to install the jack up tower crane 30How to install the jack up tower crane?
Question:

How to install the jack up tower crane 30How to install the jack up tower crane?

For example, self lifting tower crane mounted to 10 meters or 2 floor use. How do you install the third floor now? Is it necessary to remove the crane?. Then add the length of the steel frame on the base seat, and then install the crane above him If so, then 2 cranes are needed. But how is another crane installed?Ask you experts on the construction site of self lifting tower cranes how to install?. Do you use hydraulic jacks like car jacks?

Answer:

It is required from the upper plus height, then the crane through the motor (hydraulic is not I don't know if not carefully studied to estimate almost) slowly up, because the installation of crane is a separate Union, only the crane is fixed on the top, and is connected to the lower die width ratio some long, above there are for the installation of people stay small table, but also it can open from the opening above the dead ground fill and then fix it by bolt, and then put the live up to OK
Looking for technical personnel to install, you fuck what heart?.
Since it is self lifting, as the name suggests, it is on its own power that no other crane can rise. It has a special elevated section, a hydraulic device, the upper section rises, the middle empty time section, with his arm to be added to the festival hanging near the artificial it fixed, so that a section of the rising of the. Is to support themselves, and then in the middle plus standard section.
1, since it is self lifting, as the name suggests, is to rely on their own strength, without other cranes can rise.2, it has a special elevated section, a hydraulic device, the upper section rises, the middle empty time section, with his arm to be added to the festival hanging near the artificial it fixed, so that a section of the rising of the.3 crane refers to a certain range of vertical lifting and horizontal moving heavy lifting machines. Also called crane. At present the Guangdong SHUNFA hoisting lifting equipment limited company has gradually cancelled lifting driving function. The main features are: the tyre crane driving cab and lifting control room, is be made one crawler crane (crawler crane) evolved, the walking tracks and walking mechanism to support part of the tire chassis, overcome the crawler crane (crane) damage caused by the defects of trackboard pavement, belongs to the material handling machinery. Lifting equipment is characterized by intermittent exercise to do some work, namely the corresponding mechanism, taking in a working cycle of transport and unloading action is the turn of the job, the crane in the market development and the use of more and more widely. Because no leg lifting and lifting driving often appear some accident, driving faster than the crawler crane (crane); stable operation, large lifting capacity, lifting, walking road, but must ensure smooth solid tire pressure to meet the requirements, hanging from the ground not more than 50CM in a certain range is prohibited; with a load of long distance. In order to ensure the safety of operation, the lifting operations are not allowed to be carried out at home.

Share to: