In the tunnel construction, the water stop belt and the water stop strip are respectively used in what place, the construction joint and the subsidence seam many meters set a, above all has any function
5, the user should be based on the order of the project structure, design drawings to calculate the length of the product, the special-shaped structure should have drawings, as far as possible in the factory will be connected to the whole
If you need to connect in the field, you can use the electric heating plate vulcanization bonding or cold bonding (rubber water stop) or welding (plastic water stop) method, such as user connection is difficult, I can send technical personnel on-site guidance.
Fixed strip: the use of additional reinforcement fixation; special fixture fixed; the wire and fixed template (Figure 2), such as perforation, can only choose the installation area on the strip edge, not to damage other parts