Home > categories > Machinery & Equipment > Fruit & Vegetable Processing Machinery > Installation and maintenance of colloid mill
Question:

Installation and maintenance of colloid mill

Installation and maintenance of colloid mill

Answer:

5, connected to the cooling water, and pay attention to the water inlet and outlet signs.
4, check and connect the power cord (three-phase alternating current, the voltage of 380 volts, the body to protect the ground) and pay attention to the direction of rotation of the rotor should be pointing with the arrow on the same point (clockwise rotation).
3, before use, with a special trigger to rotate the rotor, check with the stator is in contact with the presence of stuck phenomenon, if the above situation does not allow the boot.
1, the level of equipment installed in the formation of the concrete foundation, and fixed with the anchor screw (according to the work can not be fixed).
If the situation is not normal should immediately stop, troubleshooting and then try to run.