Scaffolding installation and precautions?
When the structural layer is attached to the wall, the wall column, the vertical horizontal rod and the transverse horizontal rod are set up immediately after the erection of the structure.5, closed with a step horizontal bar frame must turn around the hands all around the circle, with a right angle fastener and the inner and outer post fixed.6, the horizontal horizontal pole of the double row scaffold should not be greater than 100mm from the wall to the wall.7, when the scaffolding operation of the wall of the two steps, should take temporary stability measures, even after the wall pieces can be removed before the erection.
Began to set up the column, should be set up every 6 span of a throw support, even after the installation of the wall is stable, can be removed according to the circumstances.
The backing plate and the base should be placed on the positioning line accurately.2, when the erection of the column, the outer diameter of the steel pipe is strictly prohibited, the adjacent column of the docking fasteners shall not be in the same height, staggered distance should meet the structural requirements.