Product quality certificate and inspection report. Rust must be replaced, not to be used to build the frame.
The quality standard of the foot hand frame fittings: 1, steel pipe: (1) the steel pipe adopts the outside diameter is 48mm, the wall thickness is 3.5mm, the quality standard of the foot hand frame fittings
Steel pipe: (1) steel pipe with 48mm outside diameter, wall thickness of 3.5mm steel welded pipe No. 3