Home > categories > Machinery & Equipment > Tower Cranes > Tower cranes should stop working when the wind speed is greater than the magnitude.
Question:

Tower cranes should stop working when the wind speed is greater than the magnitude.

Tower cranes should stop working when the wind speed is greater than the magnitude.

Answer:

Rules for safety regulation of tower crane,The installation of tower crane is strictly prohibited at grade 4 or above
Tower crane work is strictly prohibited at grade 4 or above
Tower crane should stop working when the regulation is greater than or equal to six wind.When the wind is greater than or equal to four, the lifting operation shall be stopped.

Share to: