What kind of personnel should be installed for the tower crane installation and disassembly?
According to GB specifications:2.0.3 the installation and disassembly of tower cranes shall be provided with the following personnel:1. The project and the safety supervisor and the mechanical management personnel who have the safety inspection certificate;2, with special construction operation qualification certificate of construction, lifting machinery, installation, demolition workers, lifting signal workers, lifting drivers, cable operators and other special operations personnel.And an electrician.
2, with special construction operation qualification certificate of construction, lifting machinery, installation, demolition workers, lifting signal workers, lifting drivers, cable operators and other special operations personnel.And an electrician.
According to GB specifications:2.0.3 the installation and disassembly of tower cranes shall be provided with the following personnel:1. The project and the safety supervisor and the mechanical management personnel who have the safety inspection certificate;