Home > categories > Construction & Real Estate > Geogrids > Which floor is paved on the roadbed
Question:

Which floor is paved on the roadbed

Which floor is paved on the roadbed

Answer:

Fixed grid end, by laying machine or manual will grill slowly pulled forward each shop, shop 10 meters long artificial investigation at a time, until a volume grating puwan, put the next volume, operation with; 3, ground shop: Volume long unit as the laying of the long, should be covered grille with long period, then the overall check again laying quality, then laying the next paragraph, a laying, grille grille to overlap a grid spacing for the lap length, tie fixed line continues to spread second section direction.
The paving surface construction method of plastic geogrid, geogrid 1 should be smooth, laying layer after acceptance, to prevent longitudinal askew phenomenon, first according to the width in laying layer or draw white thread, you can start laying, then use the U nail fixed grid end (per meter wide with a nail 4, uniform fixed distance)
Glass fiber geogrid is generally laid under the asphalt, soft foundation treatment of the geogrid as the design of the water layer in the layers of laying

Share to: