the use of sand, stone material laying, should not be lower than 0 ℃; the use of self-leveling, paint laying, not less than 5 ℃, should not be higher than 30 ℃ (New) Description: The construction of the ground floor of the construction of the provisions of the laying of the layer of the ambient temperature This is not only to make the layers with normal condensation and hardening conditions, more important is to ensure the quality of the project When the ambient temperature can not meet the construction.
the use of organic adhesive paste, should not be low At 10 ℃;
the use of mixed with cement, lime and the laying of materials and the use of taste Bai degree of fat mixed with oil asphalt cement paste, should not be less than 5 ℃;